What is ball valve installation and maintenance?

Oct 31, 2023
206

Installation and maintenance:

① Ensure that the ball valve installation position pipeline is in the coaxial position, the two flanges on the pipeline should be kept parallel to confirm that the pipeline can bear the weight of the ball valve itself. If it is found that the pipeline can not bear the weight of the ball valve, the pipeline should be supported before installation.

② Confirm whether there are impurities, welding slag and so on in the pipeline, the pipeline must be swept clean.

③ Any section of the ball valve can be installed at the upstream end, and the handle ball valve can be installed at any position of the pipeline. If the ball valve with actuator (such as gearbox, electric-pneumatic actuator) is configured, it must be installed vertically, and the valve inlet and outlet are in a horizontal position.

④ Ball valve flange and pipeline flange are fitted with gasket according to pipeline design requirements.

⑤ Bolts on the flange should be tightened symmetrically, sequentially and evenly.

⑥ Installation, start ball valve open and close several times, should be flexible, uniform force, ball valve work normally.

⑦ Valve operation according to the actuator input signal size drive stem rotation completed: forward rotation 1/4(90°), the valve closed. During reverse rotation of 1/4 laps (90°), the valve opens.

⑧ Ball valve to have valve handle rotation position.

⑨ Ball valve can not be used as throttling.

⑩ Ball valves with transmission mechanisms shall be installed upright.

válvula de bola

Common Troubleshooting of Ball Valve:

① Leakage of right valve body and left valve body. Repair the sealing surface, remove dirt, replace the gasket, and tighten the nut evenly and cross.

② Packing leakage. Tighten cover bolts or replace packing (1 upper packing ,2 middle packing ,1 lower packing). When installing, be careful not to cut the edge and tighten the cover bolt evenly.

③ Stem is not flexible. Loose cover bolts, evenly loosen left and right connection nuts or thickened gaskets to reduce pretightening force, be careful not to leak.

④ Sealing leakage. Uniform, cross tighten the left and right body connection nut, increase the pretightening force, or adjust the sealing seat, gasket and clean the sealing groove.

⑤ When the ball valve is not screwed, do not put the auxiliary lever or other tools on the wrench, which will damage the stem. If the operation of Mandarin hard to analyze the reasons, some valve closure caused by thermal expansion of the opening difficulties, this time the gland bolt can be loosened, to clear the stem stress before opening, packing too tight, can properly relax the packing.

⑥ Ball valves can only be fully open or closed, generally not allowed for adjustment and throttle. Ball valve with wrench, wrench parallel to the channel for full opening ,90° for full closure.

⑦ Sealing leakage. Uniform, cross tighten the left and right body connection nut, increase the pretightening force, or replace the sealing seat, gasket and clean the sealing groove.

Related Products
Learn more about related products
CONTACT US
Please complete your inquiry and we will contact you as soon as possible

    *All information you fill out will be guaranteed not to be disclosed to third parties.


    X
    sales@wsdsolution.com
    +86 17319732766
    +86 17319732766